Q:
It is proposed to improve the existing highway for ? 145 lakhs. Estimate the annual cost of the pavement if it to last for 15 years and the rate of interest is 6%.
A) 13.94 lakhs
|
B) 13.49 lakhs
|
C) 14.93 lakhs
| D) 14.39 lakhs
|
View Answer
Explanation