Q:

The unit of payment of cement concrete in lintels is _________

A) Per sqm B) Per cum
C) Quintal D) Kilograms
 
Answer & Explanation Answer: B) Per cum

Explanation: The unit of payment of cement concrete in lintels is per cum. The unit of payment of R.C.C. in the slab is also per cum. Here, per cum stands for per cubic metre.

View Answer Discuss

101
Q:

Calculate the number of cement bags required for RCC (1:2:4) for 15 m³ of work.

A) 24.6 B) 38.9
C) 56.7 D) 93.8
 
Answer & Explanation Answer: D) 93.8

Explanation: The quantity of cement required is [1/(1+2+4)] x 1.52 x 15 m³ i.e. 3.257 m³. SP weight of concrete is 1440 kg/m³ and the weight of one cement bag is 50 kg. Therefore, the number of cement bags required for RCC (1:2:4) for 15 m³ of work is 3.257 x 1440/50 = 93.8 bags.

View Answer Discuss

192
Q:

The quantity of coarse aggregate required for RCC (1:3:6) for 20 cubic metres of work is ________

A) 18.24 m³ B) 15.23 m³
C) 24.87 m³ D) 32.45 m³
 
Answer & Explanation Answer: A) 18.24 m³

Explanation: The ratio 1:3:6 is for cement, sand and coarse aggregate. Therefore, the quantity of coarse aggregate required for RCC (1:3:6) for 20 cubic metres of work is [6/(1+3+6)] x 1.52 x 20 m³ i.e. 18.24 m³.

View Answer Discuss

73
Q:

The quantity of sand required for RCC (1:2:4) for 15 cubic metres of work is ___________

A) 4.76 m³ B) 10.32 m³
C) 8.43 m³ D) 6.51 m³
 
Answer & Explanation Answer: D) 6.51 m³

Explanation: Approximately 1.52 m³ of dry concrete is required for 1 m³ of wet concrete. The quantity of sand required for RCC (1:2:4) for 15 cubic metres of work is [2/(1+2+4)] x 1.52 x 15 m³ i.e. 6.51 m³.

View Answer Discuss

73
Q:

Calculate the number of cement bags required for 2500 kg of cement.

A) 50 B) 100
C) 500 D) 200
 
Answer & Explanation Answer: A) 50

Explanation: The weight of one cement bag is 50 kg. Therefore, the number of cement bags required for 2500 kg of cement is 2500/50 i.e. 50 bags.

View Answer Discuss

61
Q:

The rates of materials used for government works are approved by _________

A) Executive Board B) SDO
C) Elective Board D) Board of Chief Engineers
 
Answer & Explanation Answer: D) Board of Chief Engineers

Explanation: The Board of Chief Engineers approves the rates of materials used for government works. However, every year, these are fixed by the Superintendent Engineer.

View Answer Discuss

75
Q:

Which of the following is the correct order of stages of estimation of concrete roads?

A) Earthwork excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8) B) Earthwork excavations, cement concrete for wearing course (1:4:8) and cement concrete for the base course (1:2:8)
C) Earthwork excavations, cement concrete for the base course (1:6:9) and cement concrete for wearing course (1:7:9) D) Cement concrete for the base course (1:2:3), cement concrete for wearing course (2:7:9) and earthwork excavations
 
Answer & Explanation Answer: A) Earthwork excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8)

Explanation: The correct order of stages of estimation of concrete roads is earth work excavations, cement concrete for the base course (1:4:8) and cement concrete for wearing course (1:2:8). Cement concrete road is laid over an existing Water Bound Macadam road.

View Answer Discuss

58
Q:

The concrete used for cement concrete roads is of grade ___________

A) M 10 B) M 15
C) M 20 D) M 35
 
Answer & Explanation Answer: B) M 15

Explanation: The concrete used for cement concrete roads is of grade M 15 using 20 mm hand broken grade metal. For base course, concrete of 1:4:8 is used using 40 mm HBG metal.

View Answer Discuss